The request to determine the bearing capacity of your proposed site, Plot # 52, Citadel Circular Avenue, Block-I, Gulberg Dream Villas, Islamabad was made by Skyline Developers, Islamabad to Construction Materials Testing Laboratory (CMTL) RDI, Rawat. The plot area consist of 35 x 70 size. Geotechnical studies has been carried out by excavation of 2 x test pits in depth of 12 feet below from existing ground level for evaluation of index and strength properties parameters for safe and an economical structure designing purpose. These strength and index parameters are tabulated in Anx-A of this report.
. Recommendations of bearing capacity and strength improvement technique of low strength soil of foundation durability are included.
;
Excavation of (2) Test pits at different location of plot area up to 12 ft. depth for soil profiling purpose
-
SCOPE OF TESTING:-
- SITE INVESTIGATION:-
- Standard
penetration test (N-Value) was conducted after 3 ft intervals in each test pits.
- Determination of in situ density and in situ moisture contents.
- Collection of disturbed and undisturbed soil samples for laboratory testing.
-
- TESTING AT SITE :-
Penetration Test (SPT). This test was conducted at site according to ASTM Designation D-1586. The standard
penetration blow count value “N” recorded at various depth intervals are tabulated in annex- A of this report. Average N value was reported as 4.375
- In situ density and Moisture Content Tests. In situ density and moisture content tests have been conducted in test pits and disturbed soil samples are collected from test pits as per ASTM Standard
and test results value are tabulated in annex –A of this report. Speedy Moisture Content was determined by AASHTO – 217
- Moisture Determination with Speedy
- LABORATORY TESTING:-
- RDI, Rawat as per ASTM Standard. Following properties were evaluated and results are tabulated in annex-A of this report;
- Sieve Analysis (AASHTO-88)
- Atterberg Limits (AASHTO -84-89)
- DISCUSSION OF RESULTS:-
-
- RECOMMENDATION
- Allowable bearing capacity of proposed soil was calculated as 49 tsf and Raft foundation is recommended for a firm foundation design.
- Raft foundations have the advantage of reducing differential settlements as the concrete slab resists differential movements between loading positions.
- Depth of foundation, 0 ft. should be adopted from existing road level.
- The foundation soil should be well compacted prior to laying the footing for firm setting.
- Light Earth Moving Machinery can be used for the excavation purpose.
- Foundation soil must be compacted up to 98 % of maximum dry density of soil.
- Compaction test should be carried out after excavation and then after light earth moving compacter.
- A RCC CUTOFF wall must be constructed around the building area for the better confinement of foundation. It will stop the infiltration of water from outside source (i.e. precipitation). A granular Layer of 2 feet of thickness must be provided beneath the foundation. It is highly recommended that it should be compacted to 100 % of maximum dry density of granular material.